default

Island Colony AOAO

Island Colony is a 745-unit mixed-use condominium resort in Waikiki that recently completed the largest pipe replacement project in the state to date. As Construction Project Manager, Native Technologies executed a plan and brought together a team that completed the project significantly under budget and well ahead of schedule.

Illonai 20231215003619_0012_D copy

Iolani Court Plaza AOAO

Native Technologies managed a concrete spall repair, painting, waterproofing, and sealant replacement project completed in 2022, and is currently overseeing a property-wide DWV pipe replacement scheduled for completion in 2026. At this 347-unit condominium, NT has delivered cost efficiencies, clear communication, and strong community coordination to ensure long-term building performance and resident confidence. DWV Pipe…

Royal Lolani

Royal Iolani AOAO

With new drain, waste, and vent piping installed throughout 296 units, across two towers with multiple different unit configurations, Royal Iolani residents now enjoy the many benefits of a new plumbing system.

20210902_192723130_iOS

Franklin Towers AOAO

The DWV replacement ptoject at the 156-unit Franklin Towers was yet another Native Technologies project that was completed under budget, and right on schedule. With several complexities including a related By-laws amendment and loan ballot, Native Technologies coordinated

default

Hi Sierra AOAO

Hi Sierra is a 40-unit condominium built in 1965 along Sierra Drive in Kaimuki, with sweeping views over Honolulu. In 2024, Native Technologies delivered a property-wide DWV pipe replacement, partnering with Pragmatic Engineering and SageWater. We also procured financing, coordinated owner approval via ballot with the Association’s attorney, and hosted a town hall to align…

default

Bellevue Tower AOAO

Bellevue Tower, a 25-unit Makiki condominium built in 1969, engaged Native Technologies to renew its aging DWV system. We recommended a cost-effective design/build delivery; after competitive bidding, Hawaii Plumbing Group was selected as contractor. Native Technologies led planning, permitting, coordination, and unit-access logistics through regular site visits. The project finished in 2025, renewing infrastructure with…

Nuuanu2

2040 Nuuanu AOAO

Native Technologies managed a property-wide DWV system replacement at 2040 Nuuanu with Coffman Engineers (lead designer) and Hawaii Plumbing Group (prime contractor). We handled planning, design management, bidding, financing procurement, and – working with Association counsel – owner loan approval by written consent. Completed in 2025 significantly under budget, the project renewed infrastructure with minimal…

default

1425 Punahou AOAO

1425 Punahou is an 18-unit, two-building condominium in Honolulu-one constructed in 1960, the other in 1969. Native Technologies managed a property-wide DWV pipe replacement under a design/build delivery with SageWater. We procured financing and, with Association counsel, secured owner loan approval via written consent. Completed successfully in 2025 with regular site visits and coordinated phasing.…

default

Sea View AOAO

SEA VIEW AOAO Efficient Solutions for Smaller Properties Located at the base of Punchbowl, Sea View is a 33-unit condominium of CMU construction built in 1966. Native Technologies delivered a design/build DWV pipe replacement project, including loan procurement, owner coordination, and daily management. Partnering with SageWater, the project was fully completed in just nine months,…

default

Rose Terrace AOAO

From inception through to completion, including design, financing procurement, permitting, owner education, and construction, the 55-unit DWV replacement project at Rose Terrace was completed in less than two years with total costs significantly under budget.