Highlights
Location
Honolulu
Constructed
1979
# of Units
745
Project Value
$11,000,000
Island Colony AOAO — 745 Units, On-Time DWV Delivery
The mixed-use condominium resort required intricate pre-construction phase preparation to give the aggressive construction schedule its best chance of success.
The Native Technologies team rose to the challenge by implementing a strategic communications plan, ensuring that all owners were provided at least 6 months' notice prior to in-unit construction. This gave all owners ample opportunity to plan their rental strategies accordingly.
Combined with a series of town hall meeting and detailed project bulletins, the Native Technologies Onsite Construction Manager met with ever unit representatives of every single unit to document conditions, find solution to challenges, and to provide owner representation at all times.
Joining the project team as the lead design team, Okahara & Associates provided specilized engineering services throughout the project.
SageWater was selected at the contractor for the project and didn't miss a beat, completing every unit on time, 745 times over.
NT was procured by the AOAO in May 2022. The entire project was completed in September of 2024. Delivering large projects on time is our specialty.
RELATED PROJECTS
Franklin Towers AOAO
The DWV replacement ptoject at the 156-unit Franklin Towers was yet another Native Technologies project that was completed under budget, and right on schedule. With several complexities including a related By-laws amendment and loan ballot, Native Technologies coordinated
Makiki Royal AOAO
The 40-unit Makiki Royal is a jewel in the heart of Makiki with sweeping views from every unit. Native Technologies guided the association from start to finish with a drain, waste, and vent (DWV) pipe replacement project that replaced all common area and apartment components.
Mt Terrace AOAO
The window replacement project at the 126-unit Mt. Terrace condominiums elevated the interior living spaces and the exterior appeal of the building. Native Technologies provided Construction Management Services for the complete replacement of the floor to ceiling wrap-around window system at this landmark location.
Nuuanu Place AOAO
The Board of Directors at the 20 unit Nuuanu Place turned to Native Technologies to manage their drain, waste and vent pipe (DWV) replacement project. Our design/build project solution was implemented to provide our award-winning services within an affordable budget for the smaller property.